FY 2008 HEP Targets
All HEP Facilities:
Maintain and operate HEP facilities such that unscheduled downtime is on average less than 20% of the total scheduled operating time
Proton Accelerator-Based Physics/Facilities
Deliver data as planned within 20% of the baseline estimate (800 pb-1) to CDF and D-Zero detectors at the Tevatron.
Deliver data as planned within 20% of the baseline estimate 2.0x1020 protons on target for the MINOS experiment at NuMI facility.
Electron Accelerator-Based Physics/Facilities
Deliver data as planned within 20% of the baseline estimate (25fb-1) to the BaBar detector at the SLAC B-factory. This goal was adjusted after the FY 2008 appropriation was inadequate to complete the full planned FY 2008 run of the B-factory.
Construction/Major Items of Equipment
Maintain cost and schedule milestones for upgrades and new major construction projects within 10% of baseline estimates.