Office of High Energy Physics

FY 2008 HEP Targets

All HEP Facilities:

Maintain and operate HEP facilities such that unscheduled downtime is on average less than 20% of the total scheduled operating time

Fermi and SLAC data

Proton Accelerator-Based Physics/Facilities

Deliver data as planned within 20% of the baseline estimate (800 pb-1) to CDF and D-Zero detectors at the Tevatron.

Fermi data

Deliver data as planned within 20% of the baseline estimate 2.0x1020 protons on target for the MINOS experiment at NuMI facility.

Fermi data

Electron Accelerator-Based Physics/Facilities

Deliver data as planned within 20% of the baseline estimate (25fb-1) to the BaBar detector at the SLAC B-factory. This goal was adjusted after the FY 2008 appropriation was inadequate to complete the full planned FY 2008 run of the B-factory.

SLAC data

Construction/Major Items of Equipment

Maintain cost and schedule milestones for upgrades and new major construction projects within 10% of baseline estimates.

[Project data]